The ratio of the efficiencies of two workers, P and Q, is 5 : 2. If P can complete a project in 12 days, how many days will Q take to complete the same project alone?

  1. 24 days
  2. 30 days
  3. 35 days
  4. 40 days
উত্তর দেখান ও ব্যাখ্যা

উত্তর: (B) 30 days

ব্যাখ্যা

Correct answer: (B) 30 days, as per the official SSC answer key. [Quantitative Aptitude]