SSC PYQTier 1 2025

SSC CGL – Combined Graduate Level Examination · প্রশ্ন 66

X can complete a project in 14 days, Y in 10 days. When Z joins them, the work is finished in 3.5 days. How many days would Z need alone?

  1. 8 days
  2. 8.75 days
  3. 9.33 days
  4. 10 days
উত্তর দেখান ও ব্যাখ্যা

উত্তর: (B) 8.75 days

ব্যাখ্যা

Z's rate = 2/7 − 1/14 − 1/10 = 4/35, so Z alone takes 8.75 days.