RRB NTPC · प्रश्न 32
P आणि Q अनुक्रमे 14 आणि 19 दिवसांत एक काम पूर्ण करू शकतात. ते P पासून सुरुवात करून आलटून पालटून काम करतात. संपूर्ण काम किती दिवसांत पूर्ण होईल?
उत्तर दाखवा आणि स्पष्टीकरणस्पष्टीकरण पहा
उत्तर: (A) 16 2/19 दिवस
GIVEN / CONCEPT: P can complete the work in 14 days and Q in 19 days; they work on alternate days starting with P. Step 1 (Relation / Equation): Let total work = LCM(14, 19) = 266 units ⇒ Efficiency of P = 266 / 14 = 19 units/day, and Efficiency of Q = 266 / 19 = 14 units/day Step 2 (Simplification / Calculation): Work done in 1 cycle of 2 days (P + Q) = 19 + 14 = 33 units ⇒ In 8 cycles (16 days), work completed = 8 × 33 = 264 units Step 3 (Verification / Deduction): Remaining work = 266 − 264 = 2 units; on the 17th day, P completes these 2 units in 2/19 days ⇒ Total time = 16(2/19) days RESULT / TAKEAWAY: The whole work will be completed in 16(2/19) days. Correct Answer: (a) 16 2/19 days
