SSC CGL – Combined Graduate Level Examination · ప్రశ్న 62
A, B, and C are capable of completing a job in 30, 45, and 90 days, respectively. A works every day, while B and C join A every fifth day. How long will it take to finish the task?
సమాధానం చూపించు & వివరణ
సమాధానం: (A) 25 days
వివరణ
Correct answer: (A) 25 days, as per the official SSC answer key. [Quantitative Aptitude]