The ratio of the efficiencies of two workers, P and Q, is 5 : 2. If P can complete a project in 12 days, how many days will Q take to complete the same project alone?
సమాధానం చూపించు & వివరణ
సమాధానం: (B) 30 days
వివరణ
Correct answer: (B) 30 days, as per the official SSC answer key. [Quantitative Aptitude]