EnvironmentMaharashtra PSCNews · Maharashtra

Adani Green's Tarali pumped storage project faces cost and wildlife deposit dispute

In brief

Maharashtra's Pollution Control Board has directed Adani Green Energy to stop excavation and construction at its 1,500 MW Tarali pumped storage project in Satara district, saying work at Sawarghar village lacked its permission and environmental clearance. The dispute centres on a company affidavit that revised the declared project cost from Rs 5,675 crore to Rs 56.75 crore, which would sharply cut the wildlife conservation deposit. The company says the lower figure covered only site-investigation costs. The state forest department has halted work and is probing a grievance complaint, while the company says the project lies outside the tiger reserve's buffer zone.

Key points

  1. The Maharashtra Pollution Control Board asked Adani Green Energy to stop excavation and construction work linked to the Tarali hydropower project in Satara district, citing missing permission and environmental clearance.
  2. Adani Green's affidavit reduced the declared cost of the 1,500 MW pumped storage project from Rs 5,675 crore to Rs 56.75 crore, which cut the required wildlife conservation deposit from Rs 227 crore to Rs 2.27 crore.
  3. The project is deemed to fall within the eco-sensitive zone of Koyna Wildlife Sanctuary, which forms part of the Sahyadri Tiger Reserve, so approval from the National Board for Wildlife is required.
  4. The company says the lower figure covered only site-investigation costs and that the project lies outside the notified buffer zone, while a state forest department probe into a complaint is under way.

Prelims facts

  • The Tarali Pumped Storage Project is a 1,500 MW project proposed on the Tarali dam reservoir in Satara district, Maharashtra.
  • The project's cost was declared as Rs 5,675 crore, and 4% of that (Rs 227 crore) was the wildlife conservation deposit sought by the state forest department.
  • The MoEF&CC recommended prior Environment Clearance for the Tarali PSP on February 11, 2025, citing a project cost of Rs 5,675 crore.
  • Koyna Wildlife Sanctuary is part of the Sahyadri Tiger Reserve, and the Tarali project falls in its deemed Eco-Sensitive Zone.
  • Koyna Wildlife Sanctuary lies in Satara district, which is also where the Sahyadri Tiger Reserve is located in western Maharashtra.

Key terms

Pumped Storage Project (PSP)
A hydroelectric facility that pumps water to an upper reservoir when power is cheap and releases it through turbines to generate electricity at peak demand.
Eco-Sensitive Zone (ESZ)
An area around a protected area, such as a wildlife sanctuary or tiger reserve, where human activity is regulated to reduce impact on the protected area.

Why it matters

GS3 Environment, conservation and biodiversity: eco-sensitive zones and clearance norms for projects near tiger reserves; for State PSC Maharashtra, the Koyna and Sahyadri Tiger Reserve geography.

Practice questions

Question 1 of 1
  1. The National Board for Wildlife is chaired by the Prime Minister of India.
  2. Pumped storage hydropower projects generate electricity by pumping water to an upper reservoir during periods of low demand and releasing it during peak demand.
  3. The Koyna Wildlife Sanctuary, which lies in Satara district, is located in the state of Karnataka.
How many of the above statements are correct?
Show answer and explanation

Answer: B. Only two

Statement 1 is correct, as the Prime Minister chairs the National Board for Wildlife. Statement 2 is correct, since pumped storage stores energy by pumping water uphill in surplus periods and releasing it at peak demand. Statement 3 is wrong: Koyna Wildlife Sanctuary is in Maharashtra's Satara district, not Karnataka. So two statements are correct.