Karnataka regulator proposes rising renewable procurement targets up to 43.33% by 2029-30
In brief
The Karnataka Electricity Regulatory Commission has proposed, in draft regulations for 2026, that Escoms and large consumers such as industries and commercial establishments raise their use of renewable sources such as solar, wind, hydropower and biomass. The draft sets Renewable Procurement Obligation targets rising from 35.95 per cent in 2026-27 to 43.33 per cent in 2029-30. The move follows a poor monsoon and shortages in hydro and wind generation, which have increased dependence on coal. Open-access consumers with a contracted demand of 1 MW and above are also covered.
Key points
- The Karnataka Electricity Regulatory Commission has released draft regulations on procurement of energy from renewable sources, 2026, which are still open to change.
- The draft raises the Renewable Procurement Obligation target in annual steps from 35.95 per cent in 2026-27 to 43.33 per cent in 2029-30.
- Obligated entities include Escoms and open-access consumers with a contracted demand of 1 MW and above, and wind and hydropower obligations must come from projects commissioned after March 31, 2024.
- If targets are missed, entities may buy renewable power, buy Renewable Energy Certificates or pay a buyout price fixed by the Central Electricity Regulatory Commission, and non-compliance can attract action under Section 142 of the Electricity Act, 2003.
- The proposal comes after a poor monsoon and shortfalls in hydro and wind power increased Karnataka's reliance on coal.
Prelims facts
- KERC's draft RPO targets rise from 35.95% in 2026-27 to 38.81% in 2027-28, 41.36% in 2028-29 and 43.33% in 2029-30.
- Wind and hydropower RPO obligations must be met through projects commissioned after March 31, 2024.
- Under the Electricity Act, 2003, state electricity regulatory commissions such as KERC can initiate proceedings against non-compliance under Section 142.
- Karnataka's Ballari and Raichur thermal power stations are both coal-based plants in the state's power system, and the Ballari station is supplied from Baranj coal mines.
- Renewable Energy Certificates (RECs) let obligated entities meet renewable obligations without physically consuming green power, and their redemption for compliance follows CERC regulations.
Key terms
- RPO
- Renewable Purchase Obligation: a mandated minimum share of electricity that designated consumers and distribution utilities must source from renewable energy.
- REC
- Renewable Energy Certificate: a tradable certificate representing one unit of renewable electricity, used to prove compliance with renewable obligations.
Why it matters
GS3 Infrastructure (Energy) and Climate change for UPSC; for State PSC, Karnataka's energy regulator and its renewable targets are a likely question.