Atul can do piece of work in 18 days, Aaravya is 50% more efficient than Atul. How much more time does Atul take than Aaravya to do the same piece of work?
Show answer & explanation
Answer: (B) 6
Explanation
Aaravya is 50% more efficient, so he takes 18/1.5 = 12 days. Atul takes 18 − 12 = 6 days more.