Railways PYQCBT 1 2020

RRB NTPC · Question 79

The capacity of working by A and B is in the ratio 3 : 4. If A takes 12 days to finish the work, the time taken by B to finish the same work is:

  1. 18 days

  2. 9 days

  3. 16 days

  4. 12 days

Show answer & explanation

Answer: (B) 9 days

Explanation

Time is inversely proportional to working capacity: B's time = 12 × 3/4 = 9 days.