Railways PYQCBT 1 2026MathematicsTime & Work, Pipes & Cisterns

RRB NTPC · Question 32

If 15 men working 6 hours a day can complete a work in 20 days, how many days will 18 men working 5 hours a day take to complete the same work?

  1. 24

  2. 18

  3. 15

  4. 20

Show answer & explanationShow explanation

Answer: (D) 20

Explanation

GIVEN / CONCEPT: M₁ = 15 men, H₁ = 6 hours/day, D₁ = 20 days; M₂ = 18 men, H₂ = 5 hours/day. Step 1: Using M₁ × D₁ × H₁ = M₂ × D₂ × H₂: Step 2: 15 × 20 × 6 = 18 × D₂ × 5 Step 3: 1800 = 90 × D₂ ⇒ D₂ = 1800 ÷ 90 = 20 days RESULT / TAKEAWAY: 18 men working 5 hours a day will take 20 days. Correct Answer: (d) 20