RRB NTPC · Question 32
P and Q can complete a piece of work in 14 days and 19 days, respectively. They work on alternate days, beginning with P. The whole work will be completed in:
Show answer & explanationShow explanation
Answer: (A) 16 2/19 days
GIVEN / CONCEPT: P can complete the work in 14 days and Q in 19 days; they work on alternate days starting with P. Step 1 (Relation / Equation): Let total work = LCM(14, 19) = 266 units ⇒ Efficiency of P = 266 / 14 = 19 units/day, and Efficiency of Q = 266 / 19 = 14 units/day Step 2 (Simplification / Calculation): Work done in 1 cycle of 2 days (P + Q) = 19 + 14 = 33 units ⇒ In 8 cycles (16 days), work completed = 8 × 33 = 264 units Step 3 (Verification / Deduction): Remaining work = 266 − 264 = 2 units; on the 17th day, P completes these 2 units in 2/19 days ⇒ Total time = 16(2/19) days RESULT / TAKEAWAY: The whole work will be completed in 16(2/19) days. Correct Answer: (a) 16 2/19 days