RRB NTPC · Question 86
16 men built a model in 35 days. How many days would it take for 25 men?
Show answer & explanation
Answer: (D) 22.4
Explanation
The work is 16 × 35 = 560 man-days. With 25 men it takes 560/25 = 22.4 days.
RRB NTPC · Question 86
Answer: (D) 22.4
The work is 16 × 35 = 560 man-days. With 25 men it takes 560/25 = 22.4 days.