15 persons can complete a work in 60 days. If the number of persons is increased by 5, how many days earlier will the work get completed?

  1. 20 days

  2. 10 days

  3. 15 days

  4. 45 days

Show answer & explanation

Answer: (C) 15 days

Explanation

The work = 15 × 60 = 900 person-days. With 20 persons it takes 900/20 = 45 days, i.e. 15 days earlier.