RRB NTPC · Question 59
15 men can do a work in 20 days. How many days will 10 men take to do double the same work?
Show answer & explanation
Answer: (B) 60
Explanation
The work = 15 × 20 = 300 man-days; double the work = 600. With 10 men it takes 60 days.