SSC CGL – Combined Graduate Level Examination · Question 64
A and B can do a work in 12 days and 16 days, respectively. If they work together for 6 days, then the fraction of the work left is _________.
Show answer & explanationShow explanation
Answer: (D) 1/8
Assume total work: LCM of 12 and 16 = 48 units. Efficiency of A = 48 ÷ 12 = 4 units/day; Efficiency of B = 48 ÷ 16 = 3 units/day. Work done in 6 days: Together they complete (4 + 3) × 6 = 7 × 6 = 42 units. Fraction of work left: Remaining work = 48 − 42 = 6 units. Fraction left = 6 / 48 = 1/8. Correct Answer: (d) 1/8