SSC CGL – Combined Graduate Level Examination · Question 57

X can do a job in 10 days, Y in 15 days. They work together for 4 days. What part of work remains?

  1. 1/6
  2. 1/5
  3. 1/4
  4. 1/3
Show answer & explanation

Answer: (D) 1/3

Explanation

4 × (1/10 + 1/15) = 2/3 done, so 1/3 remains.