Raj can finish a task in 18 days, and Sham can finish the same task in 27 days. They work together for 6 days. The rest of the task was finished by Raj and Tara in 3 days. How much time is required for Tara to finish this task alone?

  1. 22 days

  2. 10.8 days

  3. 12 days

  4. 15.6 days

Show answer & explanationShow explanation

Answer: (B) 10.8 days

Explanation

Total work & efficiencies: Let total work = LCM(18, 27) = 54 units. Then Raj's efficiency = 54/18 = 3 units/day, and Sham's efficiency = 54/27 = 2 units/day. Work done in first 6 days: Together Raj and Sham complete 6 × (3 + 2) = 30 units. Remaining work = 54 − 30 = 24 units. Tara's efficiency & time: Raj and Tara finish 24 units in 3 days, so (Raj + Tara) = 24/3 = 8 units/day → Tara = 8 − 3 = 5 units/day. Time for Tara alone = 54 / 5 = 10.8 days. Correct Answer: (b) 10.8 days