A piece of work is to be completed in 240 days. Due to strikes, only 75% of the days were actually worked. If the work done per working day remains constant, by what percentage should the daily work be increased to complete the work on time?

  1. 25%

  2. 30%

  3. 33.33%

  4. 40%

Show answer & explanationShow explanation

Answer: (C) 33.33%

Explanation

Actual working days: 75% of 240 = (3/4) × 240 = 180 days. Required daily work: To finish 240 units of work in 180 days, daily work must be 240/180 = 4/3 units/day instead of 1 unit/day. Percentage increase: (4/3 − 1) × 100% = (1/3) × 100% = 33.33%. Correct Answer: (c) 33.33%