SSC CHSL – Combined Higher Secondary (10+2) Level Examination · Question 67
If 6 workers can complete a task in 21 days, the time taken by 14 workers to complete the same task will be
Show answer & explanationShow explanation
Answer: (C) 9 days
Constant Work Formula: Since the number of workers and days are inversely proportional for a fixed task, M₁ × D₁ = M₂ × D₂. Substitute Values: 6 × 21 = 14 × D₂. Solve for D₂: D₂ = (6 × 21) / 14 = 126 / 14 = 9 days. Correct Answer: (c) 9 days