SSC PYQTier 1 2025

SSC CHSL – Combined Higher Secondary (10+2) Level Examination · Question 67

If 6 workers can complete a task in 21 days, the time taken by 14 workers to complete the same task will be

  1. 6 days

  2. 7 days

  3. 9 days

  4. 10.5 days

Show answer & explanationShow explanation

Answer: (C) 9 days

Explanation

Constant Work Formula: Since the number of workers and days are inversely proportional for a fixed task, M₁ × D₁ = M₂ × D₂. Substitute Values: 6 × 21 = 14 × D₂. Solve for D₂: D₂ = (6 × 21) / 14 = 126 / 14 = 9 days. Correct Answer: (c) 9 days