SSC CHSL – Combined Higher Secondary (10+2) Level Examination · Question 62
P can do a job in 15 days, Q can do the same job in 10 days. How long will they take together?
Show answer & explanationShow explanation
Answer: (B) 6 days
Take LCM of 15 and 10 = 30 units: P's rate = 30 / 15 = 2 units/day; Q's rate = 30 / 10 = 3 units/day. Combined rate: (P + Q)'s rate = 2 + 3 = 5 units/day. Time taken together: Time = 30 / 5 = 6 days. Correct Answer: (b) 6 days