UPSC PYQPrelims 2011

Civil Services Examination · Question 35

A contract on construction job specifies a penalty for delay in completion of the work beyond a certain date is as follows: ₹ 200 for the first day, ₹ 250 for the second day, ₹ 300 for the third day etc., the penalty for each succeeding day being ₹ 50 more than that of the preceding day. How much penalty should the contractor pay if he delays the work by 10 days?

  1. ₹ 4950

  2. ₹ 4250

  3. ₹ 3600

  4. ₹ 650

Show answer & explanationShow explanation

Answer: (B) ₹ 4250

Explanation

Given / Concept: The daily penalties (200, 250, 300, …) form an Arithmetic Progression (AP) with first term a = ₹ 200, common difference d = ₹ 50, and number of terms n = 10. Apply AP Sum Formula: Sum of n terms Sₙ = (n ÷ 2) × [2a + (n − 1)d]. Substitute Values: S₁₀ = (10 ÷ 2) × [2 × 200 + (10 − 1) × 50] ⇒ 5 × [400 + 450] ⇒ 5 × 850 = ₹ 4250. Result: The contractor should pay a total penalty of ₹ 4250. Shortcut: 10th day penalty = 200 + 9 × 50 = ₹ 650 (note: ₹ 650 is option (d), a trap for just the 10th day!) ⇒ Average penalty = (200 + 650) ÷ 2 = ₹ 425/day ⇒ Total for 10 days = ₹ 4250. Correct Answer: (b) ₹ 4250

Diagram explaining the answer