Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?

  1. 6 days

  2. 8 days

  3. 10 days

  4. 11 days

Show answer & explanationShow explanation

Answer: (C) 10 days

Explanation

Given: Ram and Shyam do 60% of the job in 4 days; Shyam alone does the remaining 40% in 8 days. Find daily work rates: Combined rate of (Ram + Shyam) = 60% ÷ 4 = 15% per day; Shyam's rate = 40% ÷ 8 = 5% per day. Find Ram's daily rate and time: Ram's rate = 15% − 5% = 10% per day ⇒ Time for Ram to complete 100% alone = 100% ÷ 10% = 10 days. Result: Ram would take 10 days to complete the entire job alone. Correct Answer: (c) 10 days