UPSC PYQPrelims 2016

Civil Services Examination · Question 76

W can do 25% of a work in 30 days, X can do 1/4 of the work in 10 days, Y can do 40% of the work in 40 days and Z can do 1/3 of the work in 13 days. Who will complete the work first?

  1. W

  2. X

  3. Y

  4. Z

Show answer & explanationShow explanation

Answer: (D) Z

Explanation

Given: W does 25% (1/4) in 30 days; X does 1/4 in 10 days; Y does 40% (2/5) in 40 days; Z does 1/3 in 13 days. Find time for 100% work: W = 30 × 4 = 120 days; X = 10 × 4 = 40 days; Y = 40 ÷ 0.40 = 100 days; Z = 13 × 3 = 39 days. Compare times: 39 days (Z) < 40 days (X) < 100 days (Y) < 120 days (W). Result: Z will complete the work first. Correct Answer: (d) Z

Diagram explaining the answer