Civil Services Examination · Question 80
A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50%?
Show answer & explanationShow explanation
Answer: (D) 15
Find Daily Rate / Unit Time: Let the original job be 8 units. Completing 7/8 of the job (7 units) takes 21 days ⇒ 1 unit takes 21 / 7 = 3 days. Find Total New Work: Increasing the original job (8 units) by 50% adds 0.5 × 8 = 4 units ⇒ Total work = 8 + 4 = 12 units. Find Remaining Work & Days: Work still left to finish = Total work (12 units) − Completed work (7 units) = 5 units ⇒ Days needed = 5 × 3 = 15 days. Result: It will take him 15 more days to finish the job. Correct Answer: (d) 15