UP Super TET · Question 140
21 workers can construct any wall in 25 days. If 14 more workers are deployed, then in how many days they will complete the full work?
Show answer & explanationShow explanation
Answer: (D) 15 days
Given: Initial workers M₁ = 21, initial days D₁ = 25; additional workers = 14. Formula: Since number of workers and days are inversely proportional for the same work, M₁ × D₁ = M₂ × D₂. Find new total number of workers M₂: M₂ = 21 + 14 = 35 workers. Apply M₁D₁ = M₂D₂: 21 × 25 = 35 × D₂ ⇒ D₂ = (21 × 25) / 35. Simplify: Divide 21 and 35 by 7 to get (3 × 25) / 5 = 3 × 5 = 15 days. Result: They will complete the full work in 15 days. Common mistake: Taking M₂ = 14 instead of 21 + 14 = 35. Correct Answer: (d) 15 days