21 workers can construct any wall in 25 days. If 14 more workers are deployed, then in how many days they will complete the full work?

  1. 20 days

  2. 12 days

  3. 18 days

  4. 15 days

Show answer & explanationShow explanation

Answer: (D) 15 days

Explanation

Given: Initial workers M₁ = 21, initial days D₁ = 25; additional workers = 14. Formula: Since number of workers and days are inversely proportional for the same work, M₁ × D₁ = M₂ × D₂. Find new total number of workers M₂: M₂ = 21 + 14 = 35 workers. Apply M₁D₁ = M₂D₂: 21 × 25 = 35 × D₂ ⇒ D₂ = (21 × 25) / 35. Simplify: Divide 21 and 35 by 7 to get (3 × 25) / 5 = 3 × 5 = 15 days. Result: They will complete the full work in 15 days. Common mistake: Taking M₂ = 14 instead of 21 + 14 = 35. Correct Answer: (d) 15 days