UPSC PYQPrelims 2001

Civil Services Examination · Question 141

A conveyer belt delivers baggage at the rate of 3 tons in 5 minutes, and a second conveyer belt delivers baggage at the rate of 1 ton in 2 minutes. How much time will it take to get 33 tons of baggage delivered using both the conveyer belts?

  1. 25 minutes and 30 seconds

  2. 30 minutes

  3. 35 minutes

  4. 40 minutes and 45 seconds

Show answer & explanationShow explanation

Answer: (B) 30 minutes

Explanation

Find Individual Delivery Rates: ⇒ • Rate of first conveyor belt (R₁) = 3 / 5 tons per minute = 0.6 tons/min. • Rate of second conveyor belt (R₂) = 1 / 2 ton per minute = 0.5 tons/min. Find Combined Delivery Rate: ⇒ Working together, both belts deliver: ⇒ R = R₁ + R₂ = 3/5 + 1/2 = (6 + 5)/10 = 11/10 tons per minute (= 1.1 tons/min). Calculate Time for 33 Tons: ⇒ Time required = Total baggage ÷ Combined rate ⇒ Time = 33 ÷ (11/10) = (33 × 10) / 11 = 30 minutes. Result: It will take 30 minutes to deliver 33 tons of baggage. Shortcut: In 10 minutes (LCM of 5 and 2), Belt 1 delivers 6 tons and Belt 2 delivers 5 tons = 11 tons total. To deliver 33 tons (3 × 11), it takes 3 × 10 = 30 minutes. Correct Answer: (b) 30 minutes

Diagram explaining the answer