UPSC PYQPrelims 2012

Civil Services Examination · Question 76

You are handling a time-bound project. During the project review meeting, you find that the project is likely to get delayed due to lack of cooperation of the team members. You would...

  1. Warn the team members for their non-cooperation.

  2. Look into reasons for non-cooperation.

  3. Ask for the replacement of team members.

  4. Ask for extension of time citing reasons.

Show answer & explanationShow explanation

Answer: (B) Look into reasons for non-cooperation.

Explanation

Concept: Effective project leadership requires diagnosing why team members are not cooperating so the root bottleneck can be removed in time. Evaluate Primary Option b: Looking into the reasons for non-cooperation (b) is constructive, problem-solving leadership that restores teamwork. Official UPSC Dual-Key Note: The official UPSC answer key accepts both (a) ('Warn the team members for their non-cooperation') and (b) ('Look into reasons for non-cooperation'), while rejecting (c) and (d) as escapist. Result: Option (b) (along with (a) in the official key) is the most appropriate response. Correct Answer: (b) Look into reasons for non-cooperation.

Diagram explaining the answer