You are involved in setting up a water supply project in a remote area. Full recovery of cost is impossible in any case. The income levels in the area are low and 25% of the population is below poverty line (BPL). When a decision has to be taken on pricing you would...

  1. Recommend that the supply of water be free of charge in all respects.

  2. Recommend that the users pay a one time fixed sum for the installation of taps and the usage of water be free.

  3. Recommend that a fixed monthly charge be levied only on the non-BPL families and for BPL families water should be free.

  4. Recommend that the users pay a charge based on the consumption of water with differentiated charges for non-BPL and BPL families.

Show answer & explanationShow explanation

Answer: (D) Recommend that the users pay a charge based on the consumption of water with differentiated charges for non-BPL and BPL families.

Explanation

Concept: Public utility pricing in a low-income area should balance affordability/equity (protecting BPL households), partial cost sustainability, and responsible consumption (avoiding wastage). Evaluate Primary Option d: Charging based on water consumption with differentiated (concessional) rates for BPL and non-BPL families (d) discourages wastage, partially recovers operational costs, and keeps water affordable for the poor. Official UPSC Dual-Key Note: The official UPSC answer key accepts both (c) (fixed monthly charge on non-BPL, free for BPL) and (d) (consumption-based differentiated tariff). Result: Option (d) is the most comprehensive and appropriate recommendation. Correct Answer: (d) Recommend that the users pay a charge based on the consumption of water with differentiated charges for non-BPL and BPL families.