Civil Services Examination · Question 71
A person X can complete 20% of work in 8 days and another person Y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
Show answer & explanationShow explanation
Answer: (A) 6
Given / Concept: Find the time taken by X and Y individually to complete 100% of the work. Individual Rates: X does 20% (1/5) in 8 days ⇒ 100% in 40 days (rate = 1/40 per day). Y does 25% (1/4) in 6 days ⇒ 100% in 24 days (rate = 1/24 per day). Combined Rate: Together, (X + Y)'s 1-day work = 1/40 + 1/24 = (3 + 5)/120 = 8/120 = 1/15 of the work per day. Result: Time to complete 40% (= 2/5) of the work = (2/5) ÷ (1/15) = (2/5) × 15 = 6 days. Correct Answer: (a) 6