A certain number of men can complete a piece of work in 6k days, where k is a natural number. By what percent should the number of men be increased so that the work can be completed in 5k days?

  1. 10%

  2. (50/3)%

  3. 20%

  4. 25%

Show answer & explanationShow explanation

Answer: (C) 20%

Explanation

Given / Concept: Total work W = Men × Days is constant, so M₁D₁ = M₂D₂. Find Ratio of Men: M₁ × 6k = M₂ × 5k ⇒ M₂ / M₁ = 6k / 5k = 6 / 5. Percentage Increase: Required % increase = ((M₂ − M₁) / M₁) × 100% ⇒ ((6 − 5) / 5) × 100% = (1 / 5) × 100% = 20%. Result: The number of men should be increased by 20%. Shortcut: Days change by −1/6 (from 6k to 5k), so men must change by +1/(6−1) = +1/5 = 20%. Correct Answer: (c) 20%